The Commissioning & Training for Compressed Air Systems

Start Date
February 8, 2021
End Date
February 18, 2021
Client
Power China
Location
Rumaila Power Station, Basra – Iraq.

Scope of Work

Work included The commissioning for “Air Compressed System” consist of (3 Screw Compressor, 2 Air Dryer, 4 Air Tanks) And The training for the client team on the operation & start-up for the above mentioned equipment

 

Equipment included in project

  • Oil – free screw compressor model: SO150-8, BOGE brand, QTY:3
  • Micro heat Dryer, BOGE brand, QTY:2
  • Pre-filter, BOGE brand, QTY:4
  • Air Tank, Vertical, BOGE brand, QTY:4