> Construction

Installation Structure for Boiler Roof

Start Date
June 30, 2017
End Date
July 15, 2017
Client
Gama Power System Engineering and Contacting INC
Location
Hartha Power Station Unit 4 — Basra, Iraq

Scope of Work

SCSO carried out all Installation of Roof at Boiler Area and supplied all required materials and provide all required machinery and equipment to execute the Works.

SERVICES PROVIDED BY SCSO:

  • Supply and provide of all required tools, hand tools, consumables, materials.
  • Providing all required health and safety materials (including but not limited to; all safety warning signs, tags, band, strip and all required health and safety materials) and ensure use of health and safety materials
  • Supply, installation, checking, inspection, maintenance, modification and dismantling of scaffolding required for execution of the Works.
  • Remove the existing roof.
  • Supplying and installation of sandwich panels (Thickness 1mm).
  • Clean the area after finishing work.