Installation of Lighting System for Boiler

Start Date
May 25, 2017
End Date
July 25, 2017
Client
Gama Power System Engineering and Contacting INC
Location
Hartha Power Station Unit 4 — Basra, Iraq

Scope of Work

SCSO carried out all Lighting of Boiler Works accordance with Subcontract Agreement, also supplied all required materials and provided all required machinery and equipment to execute the Works.

 

SERVICES PROVIDED BY SCSO

  • Supply and provide of all required tools, hand tools, consumables, materials, including inhibitor chemical Trisodium Phosphate.
  • Providing all required health and safety materials (including but not limited to; all safety warning signs, tags, band, strip and all required health and safety materials) and ensure use of health and safety materials
  • Execute all works considering the basic plan document given in the contract.
  • Preparation of Method of Statement and ITP documents prior to commencement of the Works
  • Preparation and periodically submission of Progress Report.
  • Ensure safety of working area during the execution of the works.
  • Ensure and obey quality conditions of the project during the execution of the works.
  • Supply all required machinery and equipment for execution of work. The required equipment are given in the basic plan document.
  • Clean the area after work is complete.
  • Provide manpower for 3 shifts / 24 hours working period in a day.