It was be scheduled after the completion of routine testing as defined in IEC 61439-2 and carried out at the manufacturing location.

The purpose of the Factory Acceptance Test (FAT) is to inspect the switchgear as well as the control cabinet CRA01 for conformity with the latest issue of approved drawings and data of purchase order. The FAT is a project-specific inspection of equipment and manufacturing documentation that may be witnessed by the Purchaser or its representative.

 

The FAT procedure included:

  • Visual Inspection for all Panels.
  • Mechanical Inspection.
  • Electrical Inspection.